|
Education Law Center’s latest Abbott School
Construction Program status reports (projects
completed, projects
under construction, and 52
Projects – NJSDA’s 2008 Capital Plan
analyze data from the New Jersey Schools Development Authority
(NJSDA), the Department of Education (DOE), and the Abbott
districts.
80 projects have been completed by the
State under the Schools Construction Corporation (NJSCC) and/or
NJSDA. (NJSCC was reorganized by the Governor in July
2007
and is now NJSDA). 18 projects are now under construction
by NJSDA.
The NJ Legislature’s approval and
the Governor’s signature (July 2008) on legislation
authorizing $3.9 billion in bond financing for a "second wave"
of school construction was long overdue. $2.9 million of this
funding package will fund Abbott projects and will help replace
some of the dilapidated and outmoded school facilities in
these communities and restart many projects on hold since
2005. The additional $1 billion of new funding will be given
out as project grants to non-Abbott districts (sometimes called
Regular Operating Districts or RODs) and vocational schools.
In August 2008, the NJSDA issued the list
of 52 Abbott projects to be completed with the new funding.
Non-Abbott projects will be subject to a needs-based
prioritization process
established by the DOE. The first round of non-Abbott projects
will be approved early in 2009.
Key background
information for school facilities project status:
- In the School Funding Reform Act
of 2008, Abbott districts were designated as SDA districts.
- In early 2005, Acting Governor Codey
ordered the Inspector General to review the fiscal status
of NJSCC. The IG’s subsequent April 2005 report
highlighted serious management and financial problems. All
new contracts and change orders were put on hold.
- NJSCC announced in July 2005 that
59
Abbott Projects would be completed with the
funds available at that time. These projects were considered
part of the "2005 Capital Plan."
- Due to lack of funds, the 2005 Capital
Plan was revised in April 2007 and only 32 projects were
scheduled for completion. Bid documents were to be completed
for the remaining 27, but construction was placed on hold.
With the new 2008 funding allocation, the remaining projects
from the original Capital Plan will be constructed as part
of the 2008 Capital Plan.
- Other projects placed on hold by
order of the IG in 2005 due to lack of funds remained stalled.
This process was accomplished by suspending some architectural
and engineering contracts. These projects were frequently
cited as the "list of 97". Some of the projects
on the list were incorrect or, in the interim, have been
changed. ELC made the necessary corrections to the list
of 97
called "Projects outside of the 2005 Capital Plan"
and added the estimate of expenditures on those projects
at that time. The 2008 status of those projects is noted
in the Comments column.
- In summary, the 52 newly funded
projects in the 2008 Capital Plan include projects from
the original NJSCC 2005 Capital Plan and additional projects
from Abbott districts priority lists drawn up as part of
the Long Range Facilities Plans. Many of the priority projects
on the districts’ lists have been on hold since 2005 and
were in the list of "Projects outside the 2005 Capital
Plan".
- NJSDA has announced that the health
and safety work
needed to maintain current buildings will also proceed as
a result of the new 2008 funding allocation.
Note: Since the establishment of
the school construction program, obtaining comprehensive,
accurate information from the NJSDA and DOE on project development
has been very difficult. NJSDA now has their list of completed
projects and projects under construction available on the
main page of their website. Some discrepancies continue to
exist between reports issued by these two agencies and ELC’s
district surveys.
The identification of a school facility
"project" by SDA accounts for the major difference. The
2000 Educational Facilities Construction and Financing Act
(EFCFA) does not distinguish between the type and scope of
projects. ELC and DOE consider a school facility project to
be all work associated with the design and construction of
either an entirely new building, an addition to a school building,
a conversion of a building not previously used as a school,
or a substantial renovation of an existing school facility
resulting in the creation of instructional spaces. NJSDA customarily
uses the term "project" to describe discrete scopes
of work as defined by the terms of a contract. The result
is that NJSDA designated projects may be a component or phase
of a larger project, a facility serving multiple schools,
or simply a repair to an existing facility (health and safety
project).
|