|
Education
Law Centers latest Abbott School Construction Program
status reports (projects
completed, projects
under construction, and 59
Abbott Projects in NJSDA's Capital Plan and the
list of Stalled Projects) analyze data from the
NJ Schools Development Authority, the Department of Education
and the Abbott districts.
ELC has added a list of 91 stalled projects with expenditures
to date to highlight the amount of funds already spent on
land and design. According to ELC's Executive Director, David
Sciarra, "Leaving these projects stranded makes no economic
sense. Millions have already been sunk into the projects and,
with construction costs rising, the price-tag goes up every
day. School construction also generates substantial wage,
sales, and other revenue for the treasury. And, most importantly,
we must make sure every child attends a school that is safe,
not overcrowded, and sufficient to deliver the high quality
education he or she deserves."
Key
information from ELC concerning school facilities projects:
- 71
projects have been completed. (see definition of a project
below)
- 28
projects are under construction.
- NJSDA
announced in July 2005 that 59
Abbott "projects" would be completed with the
remaining funds available. These projects were considered
part of the "capital plan." Due to lack of funds, NJSDA
has revised the list. Only 32 projects will proceed to completion.
Bid documents will be completed for the remaining 27, but
construction will not be initiated until additional funding
is available.
- The
27 projects on hold in NJSDA's capital plan will proceed
through design to construction documents (ready to be bid
for construction). Expenditures cited include only funds
paid out to date primarily for design, land acquisition,
relocation and remediation. In some cases, the expenditures
are very significant, for example, $40.3 million for the
Beth Israel site in Passaic. Costs for health and safety
work completed to maintain current buildings until major
work proceeds are not included in the expenditure totals.
-
In addition to the projects on hold from the list of 59,
approximately 91 other projects are stalled due to lack
of funds - architectural contracts are on hold - in April
2005 by order of Inspector General Mary Jane Cooper. These
projects are frequently cited as the list of 97. Some of
the projects on the original list were incorrect or, in
the interim, have been changed. ELC has reviewed the list,
made appropriate adjustments, and added the estimate of
expenditures on the projects to date. Expenditures for these
projects include $12.6 million for the Gloucester City Middle
School, $10.8 million for Eastside high School in Newark,
$19 million for University High School in Newark, and $16.3
million for the Phillipsburg High School.
- A
more accurate assessment of projects that will proceed from
the list of 91 stalled projects will be available after
approval of the 2005 Long Range Facilities Plans. The DOE
review of the 2005 LRFPs has not been completed as of January
2008 - 23 Abbott districts have received LRFP approval letters.
Two districts have draft approval letters.. The remaining
six districts need to correct some problems in their plans
before approval is possible.
These
reports are offered with some reservations because of NJSDA's
definition of a project. Until recently, obtaining
comprehensive, accurate information from the NJSDA and DOE
on project development was very difficult. Major discrepancies
continue to exist between reports issued by these two agencies
and ELC's district surveys. In addition, until recently, NJSDA
did not post this information on their website. NJSDA now
has their list of completed projects and projects under construction
available on the main page of their website.
The
definition of a "school facility project" remains the major
disagreement. The Educational Facilities Construction and
Financing Act (EFCFA) does not distinguish between the type
and scope of projects. ELC and DOE consider a school facility
project to be all work associated with the design and construction
of either an entirely new building, an addition to a school
building, a conversion of a building not previously used as
a school, or a substantial renovation of an existing school
facility resulting in the creation of instructional spaces.
NJSDA customarily uses the term "project" to describe discrete
scopes of work as defined by the terms of a contract. The
result is that NJSDA designated projects may be a component
or phase of a larger project, a facility serving multiple
schools, or simply a repair to an existing facility (health
and safety project).
|