| ELC's List of Abbott Facilities Projects
Under Construction by SCC (now SDA) |
| Prepared by ELC January 2008 |
| County |
Legislative District |
School District |
School Name |
Contract Type |
Comments |
| Cumberland |
3 |
Bridgeton |
High School |
ADD/REHAB |
To open 8-08 |
| Camden |
5 |
Camden |
E.C. Development Center |
NEW |
Environmental issues delayed project.
To open 8-08. |
| |
|
|
H.B. Wilson E.S. |
NEW |
In SCC Capital Plan. To open 10-08. |
| |
|
|
Dudley E.S. |
NEW |
In SCC Capital Plan. |
| Burlington |
7 |
Burlington City |
High School |
ADD/REHAB |
To open 8-08. |
| Monmouth |
11 |
Neptune Twp |
Community School |
NEW |
To open 7-08. |
| Mercer |
15 |
Trenton |
King/Jefferson PreK-8 |
NEW |
Stop work order issued due to dispute
over soil contamination. Decision reached to tear down construction
to date. |
| |
|
|
Daylight-Twilight High School |
NEW |
Demonstration Project |
| Middlesex |
17 |
New Brunswick |
High School |
NEW |
Demonstration Project |
| Union |
20 |
Elizabeth |
P.S. 21 Elementary |
ADD/REHAB |
In SCC Capital Plan. To open 9-08. |
| |
|
|
Juan Pablo Duarte-Jose Julian
Marti E.S. #28 |
NEW |
In SCC Capital Plan. To open 6-08. |
| |
|
|
P.S. 27 Elementary |
NEW |
In SCC Capital Plan. To open 8-08. |
| Union |
22 |
Plainfield |
Emerson E.S. |
NEW |
In SCC Capital Plan. To open 1-08. |
| Essex |
27 |
Orange |
Park Ave. E.S. |
ADD/REHAB |
In SCC Capital Plan. To open 11-08. |
| |
|
|
Lincoln E.S. |
ADD/REHAB |
In SCC Capital Plan |
| Essex |
27,28,29 |
Newark |
Central High School |
NEW |
To open 3-08. |
| |
|
|
Speedway E.S. |
NEW |
In SCC Capital Plan |
| |
|
|
Park PreK-8 |
NEW |
In SCC Capital Plan |
| Hudson |
33 |
Union City |
Union City High School |
NEW |
Demonstration Project |
| Hudson |
33 |
West New York |
P.S. #3 |
NEW |
In SCC Capital Plan |
| |
|
|
P.S. #2 |
REHAB |
In SCC Capital Plan |
| Essex |
34 |
East Orange |
Garvin ECC |
ADD/REHAB |
In SCC Capital Plan. To open 6-08. |
| |
|
|
P.S. #5 E.S. |
NEW |
In SCC Capital Plan. To open 12-08. |
| |
|
|
Performing Arts Prek-12 |
NEW |
Demonstration Project |
| Passaic |
35 |
Paterson |
E.S. #24 |
ADD/REHAB |
In SCC Capital Plan. To open 1-08. |
| |
|
|
International H.S. |
NEW |
In SCC Capital Plan. To open 5-08. |
| Passaic |
36 |
Passaic City |
E.S. at Main Ave |
NEW |
In SCC Capital Plan |
| Middlesex |
19 |
Perth Amboy |
E.C.C. II |
NEW |
In SCC Capital Plan. To open 8-08. |