ELC's List of Abbott Facilities Projects Under Construction by SCC (now SDA)
Prepared by ELC September 2008
County Legislative District School District School Name Contract Type Comments
Cumberland 3 Bridgeton High School ADD/REHAB  
Camden 5 Camden E.C. Development Center NEW Environmental issues delayed project.
      H.B. Wilson E.S. NEW In SCC Capital Plan.
      Dudley E.S. NEW In SCC Capital Plan.
Mercer 15 Trenton King/Jefferson PreK-8 NEW Stop work order issued due to dispute over soil contamination. Decision reached to tear down work completed. New construction has resumed.
Middlesex 17 New Brunswick High School NEW Demonstration Project
Union 20 Elizabeth P.S. 21 Elementary ADD/REHAB In SCC Capital Plan. To open 9-08.?
      Juan Pablo Duarte-Jose Julian Marti E.S. #28 NEW In SCC Capital Plan. To open 6-08.?
Essex 27 Orange Lincoln E.S. ADD/REHAB In SCC Capital Plan.
Essex 27,28,29 Newark Speedway E.S. NEW In SCC Capital Plan.
      Park PreK-8 NEW In SCC Capital Plan
Hudson 33 Union City Union City High School NEW Demonstration Project.
Hudson 33 West New York P.S. #3 NEW In SCC Capital Plan.
      P.S. #2 REHAB In SCC Capital Plan.
Essex 34 East Orange P.S. #5 E.S. NEW In SCC Capital Plan. To open 12-08.
      Performing Arts Prek-12 NEW Demonstration Project.
Passaic 36 Passaic City E.S. at Main Ave NEW In SCC Capital Plan
Middlesex 19 Perth Amboy E.C.C. II NEW In SCC Capital Plan. To open 8-08?