List of Abbott Facility Projects - 2005 Capital Plan (referred to as the "list of 59")
Updated Sept. 2008 with Revisions from April 2007 and New Funding in 2008
 
County Legislative District School District School Name Contract Type Comments
Cumberland 1 Vineland Vineland M.S. #2 NEW Original architectural contract cancelled, SCC hired new architect. Project was on hold due to lack of funding. Expenditure on project to date: $2.6 million. Now funded with 2008 allocation.
Atlantic 2 Pleasantville Decatur Ave Alt HS CONVERSION Project was on hold due to lack of funding. Expenditure on project to date: $1.1 million. Now funded with 2008 allocation.
Burlington 8 Pemberton Early Childhood Center NEW Project was on hold due to lack of funding. Expenditure on project to date: $2.5 million. Now funded with 2008 allocation.
Monmouth 11 Asbury Park Middle School ADD/REHAB Project now on hold due to lack of funding. Status unknown. Expenditure on project to date: $2.7 million.
Monmouth 11 Long Branch Gregory E.S. NEW Completed and open.
      Elberon E.S. ADD/REHAB Project was on hold due to lack of funding. Expenditure on project to date: $1.2 million. Now funded with 2008 allocation.
Monmouth 13 Keansburg Lorraine Place E.S. NEW Project was on hold due to lack of funding. Expenditure on project to date: $5.3 million. Now funded with 2008 allocation.
Camden 14 Camden Dudley E.S. NEW (Design build) Under Construction.
      H.B. Wilson E.S. NEW Under Construction.
      Morgan Village Jr. H.S. REPLACEMENT Status Unknown. Expenditure on project to date: $4.0 million.
      Pyne Point M.S. ADD/REHAB Recent contamination found under TCUs on the site. Project was on hold due to lack of funding. Expenditure on project to date: $6.3 million. Now funded with 2008 allocation.
Mercer 15 Trenton Roebling PreK-8 CONVERSION Project was on hold due to lack of funding. Expenditure on project to date: $18.3 million. Now funded with 2008 allocation.
      ECC NEW (design build?) Project was on hold due to lack of funding. Expenditure on project to date: $1.8 million. Now funded with 2008 allocation.
      High School NEW Project was on hold due to lack of funding. Expenditure on project to date: $10.3 million. Now funded with 2008 allocation.
Middlesex 17 New Brunswick Redshaw E.S. NEW Project was on hold due to lack of funding. Expenditure on project to date: $3.5 million. Now funded with 2008 allocation.
      Robeson Community E.S. ADD/REHAB Project was on hold due to lack of funding. Expenditure on project to date: $1.9 million. Now funded with 2008 allocation.
      K Center 3 NEW Completed and open.
Middlesex 19 Perth Amboy Seaman Ave.E.S. NEW Project was on hold due to lack of funding. Expenditure on project to date: $2.3 million. Now funded with 2008 allocation.
      E.C.C. II NEW Under Construction.
Union 20 Elizabeth P.S. 21 E.S. ADD/REHAB Under Construction.
      P.S. 27 E.S. NEW Completed and open.
      P.S. 28 E.S. NEW Under Construction.
Union 22 Plainfield Emerson E.S. NEW Completed and open.
Essex 27 Orange Lincoln E.S. ADD/REHAB Under Construction
      Park Ave. E.S. ADD/REHAB Completed and open.
Essex 28 Irvington Augusta E.S. ADD/REHAB Completed and open.
Essex 27,28,29 Newark West Side H.S. ADD/REHAB Cannot begin until Central HS is complete; removed from list of "59"., but now funded under the 2008 allocation. Expenditure on project to date: $9.7 million.
      Elliot Street preK-8 NEW Substituted on list for West Side HS, replacement for building destroyed by fire in 2006. SDA has had delays for demolition of old building and in hiring an architect. Project now going forward. Expenditures on project to date by SDA: $2.4 million. Most of the cost for new project will be paid by insurance.
      First Avenue preK-8 NEW Completed and open.
      Speedway Ave preK-8 NEW Under construction.
      Park PreK-8 NEW Completed and open.
      Gladys Hillman-Jones 5-8 ADD/REHAB Project was on hold due to lack of funding. Expenditure on project to date: $4.8 million. Now funded with 2008 allocation.
Hudson 31,32,33 Jersey City P.S 24 E.S. ADD/REHAB Project now on hold due to lack of funding. Status Unknown. Expenditure on project to date: $4.5 million.
      ECC #03 NEW Project was on hold due to lack of funding. Expenditure on project to date: $7.8 million Now funded with 2008 allocation.
      ECC #13 NEW Project was on hold due to lack of funding. Expenditure on project to date: $3.2 million. Now funded with 2008 allocation.
      ECC #14 NEW Project was on hold due to lack of funding. Expenditure on project to date: $450,000 thousand. Now funded with 2008 allocation.
Hudson 33 Hoboken Calabro E.S. REHAB Completed and open.
      T. Connors E.S. REHAB Project was on hold due to lack of funding. Expenditure on project to date: $771,000. Now funded with 2008 allocation.
Hudson 33 Union City Columbus K-5 NEW Project now on hold due to lack of funding. Expenditure on project to date: $7.7 million. Now funded with 2008 allocation.
Hudson 33 West New York P.S. #2 REHAB Under construction.
      P.S. #3 NEW Under Construction.
      Henry L. Bain #6 E.S. NEW Project was on hold due to lack of funding. Expenditure on project to date: $8.5 million. Now funded with 2008 allocation.
Essex 34 East Orange P.S. #5 E.S. NEW Under Construction.
      Garvin ECC ADD/REHAB Completed and open.
Passaic 35 Paterson International H.S. NEW Completed and open.
      R. Clemente ES/K Center. REHAB K Center scheduled for construction 10-07. ES completed and open. Expenditure on project to date: $2.1 million including Health and Safety work to keep old building in use. Status unknown.
      E.S. #25 ADDITION Project was on hold due to lack of funding. Expenditure on project to date: $1.1 million. Now funded with 2008 allocation.
      E.S. #24 ADD/REHAB Completed and open; land is needed for parking.
      Marshall St. E.S. NEW Project and Marshall Street Pedestrian Bridge was on hold due to lack of funding. Expenditure on project to date: $8.8 million. Now funded with 2008 allocation.
Bergen 36 Garfield James Madison E.S.# 10 NEW Project was on hold due to lack of funding. Present owner sued to stop construction. Expenditure on project to date: $2.6 million. Now funded with 2008 allocation.
Passaic 36 Passaic Dayton Ave Campus M.S.. E.S. and ECC NEW Projects were on hold due to lack of funding. Beth Israel site was purchased. Expenditure on project to date: $28 million. Now funded with 2008 allocation.
      Henry Street E.S. NEW Project was on hold due to lack of funding. Expenditure on project to date: $692,000. Now funded with 2008 allocation.
      E.S. at Main Ave NEW Under Construction
Additional Work on original SCC List of 59 - Not Full Projects
Middlesex 19 Perth Amboy High School (Athletic Field)   High school building is a district priority but has not been funded.
Essex 27,28,29 Newark List of Health and Safety Work,   Some of these projects have moved forward.
Hudson 32 Harrison High School Synthetic Turf   Completed.
Hudson 31,32,33 Jersey City P.S. 34 Health and Safety Completed.
Hudson 33 Union City Jose Marti Athletic Field School Completed Field completed.
Changes since July 2005 SCC decisions
Warren 23 Phillipsburg High School Field and Site Work   Completed.
  Demonstration Projects
Cumberland 1 Vineland Community School NEW Completed and open.
Camden 14 Camden Catto Elementary NEW Completed and open
Mercer 15 Trenton Daylight-Twilight H.S. NEW + Conversion Completed and open.
Middlesex 17 New Brunswick High School NEW Contract Awarded 4-07
Hudson 33 Union City Union City High School NEW Under Construction
Essex 34 East Orange Performing Arts Prek-12 NEW Under Construction